Project Costing
Build up a project's total cost from labour hours, materials, subcontractors and overhead, then compare it to the agreed price to see the margin, cost variance and earned value.
Gegevens gecontroleerd · juli 2026
What if I don't have a separate budgeted cost for the project?
Leave budgeted cost and percentage complete at their defaults — the calculator will still compute total cost, profit and margin against the project price; only the cost variance and earned value require a budget figure.
Bron: CIMA — Job, batch and contract costing topic guide; ACCA Management Accounting (MA), project and contract costing methods. · bijgewerkt 2026
🧮
Vul de velden in om de resultaten in realtime te zien
Bevalt deze rekenmachine u?
Maak een gratis account aan om uw berekeningen op te slaan, de geschiedenis te bekijken en als PDF te exporteren. Upgrade naar Pro voor alle 319 rekenmachines.
Een vraag over dit resultaat?
Stel deze aan Solva, de AI-financieel adviseur van ActioFin — antwoorden gebaseerd op officiële teksten.
5 gratis vragen per dag met een gratis account
Alles over Project Costing
📋Overzicht+
Project costing pulls together labour (hours times rate), direct materials, subcontractor costs and other direct costs into a total direct cost, then adds an overhead recovery based on a chosen overhead rate. Comparing the total cost to the agreed project price gives the profit and margin, while comparing it to a separate budget and percentage complete gives a cost variance and earned value — useful for tracking a project's financial health while it is still in progress.
💡 Best practices
- Track percentage complete against milestones or measurable output, not against time elapsed — time-based estimates routinely overstate real progress on projects that stall.
- A cost variance that keeps growing project over project usually points to underestimating either labour hours or the overhead rate at the quoting stage, not a one-off issue.
- Revisit the overhead rate periodically against actual overhead spend — a rate set years ago rarely still reflects current costs.
🔢 Concreet voorbeeld
120 labour hours at £35/hour, £8,000 materials and £3,000 subcontractor cost, 15% overhead, against a £30,000 project price: a healthy margin with room for the overhead recovery.
📖Handleiding+
Zo gebruikt u deze rekentool
- 1
Enter the labour hours worked and the labour rate per hour.
- 2
Enter materials, subcontractor and other direct costs.
- 3
Enter the overhead rate to apply, and the agreed project price.
- 4
If tracking an in-progress project, enter the budgeted cost and percentage complete for the variance and earned value.
📚Woordenlijst+
- Earned value
- The budgeted cost of work actually performed to date, calculated as the budgeted cost multiplied by the percentage of the project complete — used to compare planned progress to actual cost incurred.
- Overhead recovery rate
- The percentage applied to direct costs to recover a fair share of indirect overheads (office costs, equipment, supervision) not directly traceable to a single project.
ℹ️Bronnen & updates+
Laatste gegevensupdate
7 juli 2026
Bronnen en referenties
CIMA — Job, batch and contract costing topic guide; ACCA Management Accounting (MA), project and contract costing methods.
De gegevens van deze rekentool worden regelmatig bijgewerkt volgens de laatste officiële tarieven. Raadpleeg bij twijfel de bovenstaande officiële bronnen.
FAQ — Project Costing
What if I don't have a separate budgeted cost for the project?+
Leave budgeted cost and percentage complete at their defaults — the calculator will still compute total cost, profit and margin against the project price; only the cost variance and earned value require a budget figure.
Is the overhead rate applied to labour only or to all direct costs?+
The overhead rate is applied to the combined direct costs (labour, materials, subcontractors and other direct costs) to give a single overhead recovery figure added to the total cost.